How we plan building engineering.
Our engineers walk rounds and log readings. Planned preventive maintenance puts every piece of equipment on a register, rates each task and sets the schedule those rounds follow.
| Unit | Observations | Status |
|---|---|---|
| Emergency generator | Starts on test, operable | Surveyed |
| Backflow preventer | Tagged, annual test due | Surveyed |
| Rooftop unit RTU-1 | Dirty coil, belts worn | Surveyed |
| Booster pump | Normal pressure, quiet | Surveyed |
| Server room cooling unit | Keeps the server room online | Surveyed |
Emergency generator3 tasks
Run under load5 stepsCritical
- Check fuel, oil and coolant levels
- Start the generator and bring it up to load
- Record voltage, frequency and run time
- Watch for leaks, smoke or alarms
- Return it to standby and log the run
- Battery and charger check4 stepsImportant
- Fuel sample and tank check4 stepsRecommended
Backflow preventer2 tasks
Annual test5 stepsCritical
- Tell the building before the water is shut off
- Connect the test kit and record each reading
- Compare the readings to the pass limits
- Tag the device and restore the water
- File the test report
- Leak and valve check3 stepsRecommended
Rooftop unit RTU-14 tasks
- Smoke detector shutdown test4 stepsCritical
- Filter and belt change6 stepsImportant
Condenser coil cleaning5 stepsRecommended
- Lock out the unit and put on the required protective gear
- Protect the surroundings and apply the approved coil cleaner
- Rinse the coil and check for clear airflow across the full face
- Put the guards back and photograph the cleaned coil
- Clean up and dispose of the rinse water to site rules
- Thermal scan of electrical connections4 stepsPremium
Booster pump3 tasks
Look, listen, log the reading5 stepsRecommended
- Check suction and discharge pressure
- Listen for bearing or cavitation noise
- Feel the motor for heat and vibration
- Look for leaks at seals and fittings
- Log the readings
- Motor amp reading3 stepsImportant
- Coupling and alignment check4 stepsRecommended
Server room cooling unit4 tasks
- Filter change3 stepsImportant
- Condensate drain and pan check4 stepsRecommended
- High temperature alarm test3 stepsRecommended
Extra coil and filter service5 stepsPremium
- Confirm the room can run on backup cooling
- Shut down and lock out the unit
- Change the filters and rinse the coil
- Restart and confirm the supply temperature
- Log readings and photos
5 units, 16 tasks in all. Open any one to see its tasks and steps.
| Unit | Every round | Monthly12 visits a year | Quarterly4 visits a year | Annual1 visit a year |
|---|---|---|---|---|
| Emergency generator | Run under load | Battery and charger check | Fuel sample and tank check | |
| Backflow preventer | Leak and valve check | Annual test | ||
| Rooftop unit RTU-1 | Filter and belt change | Smoke detector shutdown testCondenser coil cleaningThermal scan of electrical connections | ||
| Booster pump | Look, listen, log the reading | Motor amp reading | Coupling and alignment check | |
| Server room cooling unit | High temperature alarm test | Filter changeCondensate drain and pan checkExtra coil and filter service |
| Tasks | Two premium tasks held for later | 16 tasks 14 tasks |
| Time | Minutes trimmed on recommended tasks | 46 hours a year 40 hours a year |
| Frequency | One recommended task moved | Quarterly Twice a year |
Critical tasks stay on.
| How far it goes | How we rate each task | Tasks |
|---|---|---|
| Critical | Must be done. We don't compromise on it. | 3 |
| Important | Should be done. Protects the equipment. | 7 |
| Recommended | Worth doing. Prevents problems later. | 14 |
| Premium | For taking the best possible care of it. | 16 |
| Work order | Task | Linked to | Status |
|---|---|---|---|
| WO-1041 | Run under loadEmergency generator | ServiceChannel | OpenDone |
| WO-1042 | Annual testBackflow preventer | CorrigoPro | OpenDone |
| WO-1043 | Filters and beltsRooftop unit RTU-1 | ServiceTitan | OpenDone |
| WO-1044 | Look, listen, log the readingBooster pump | MaintainX | OpenDone |
| WO-1045 | Extra coil and filter serviceServer room cooling unit | ServiceChannel | OpenDone |
| Task | What the year showed | Next year |
|---|---|---|
| Run under loadEmergency generator | As expected | Monthly |
| Annual testBackflow preventer | As expected | Annual |
| Filters and beltsRooftop unit RTU-1 | Filters loading up early | Quarterly Monthly |
| Look, listen, log the readingBooster pump | As expected | Every round |
| Extra coil and filter serviceServer room cooling unit | As expected | Quarterly |
Six steps, in order.
Each step leaves a record. Scroll to watch an example fill in.
Register the equipment
We list the mechanical, electrical, plumbing and life-safety equipment in the building. The register is kept in M5's own system, and you get a login to it.
Record:Equipment registerRate the tasks
Each piece of equipment gets its tasks. Most have several, and each task has written steps our team follows. Each task gets one of four ratings: critical, important, recommended or premium. Work required by code or law is critical.
Record:Rating for each taskSet the schedule
How often a task is done follows its rating. The manufacturer's manual is one input. How much the building depends on that equipment is the other.
Record:Maintenance scheduleChoose how far the plan goes
The proposal shows what each rating covers. You can stop at critical work or go all the way through premium. Tell us your budget and we show what it covers. We fit the plan to it by adjusting which tasks are in, the time on each task and how often it runs. Critical tasks stay on. Premium is best kept for mission-critical equipment: the one piece that keeps everything in the building running and your business online.
Record:ProposalEngineers do the work
A stationary engineer does scheduled tasks during daily rounds. A roving engineer does them on a route of scheduled visits. Both log each task as it is done.
Record:Round and visit logsReview the plan every year
Readings and findings go on the record for that equipment. Once a year we review the plan with you. We go through the reports, the findings and the past work orders, then adjust the tasks, the schedule and the price for the year ahead. Each year the plan fits the property more closely.
Record:Annual review
What goes on the register.
The equipment our engineers look after, by system.
| No. | System | Equipment |
|---|---|---|
| 1 | HVAC | Rooftop units, air handlers, split systems, exhaust fans |
| 2 | Boilers and chillers | Boilers, chillers, water loops |
| 3 | Pumps and plumbing | Booster pumps, circulators, fixtures, backflow preventers |
| 4 | Electrical | Panels, lighting controls |
| 5 | Life-safety equipment | Generators, transfer switches, emergency lighting |
| 6 | Building automation | Schedules, setpoints, alarms, trend logs |
Questions
- We keep calling in the same repairs. Can that become a plan?
- Yes. We look at the work orders you have sent us over time and find the ones that come back on a pattern. We group them and propose a planned maintenance agreement that does that work on a schedule, before it turns into a call. Planned work can cost less than the same work called in one ticket at a time. It works for us too. The work is agreed for a few years, so we can plan our crews around it.
- What happens when a task is bigger than one engineer?
- Your account manager sends the rest of the team. Each property has one account manager, and our staff are trained and certified across the trades.
- Does this work for a building without a full-time engineer?
- Yes. A roving engineer does the scheduled tasks on a route of visits and logs each one.
- Do we have to change work order systems?
- No. The register is kept in M5's system. Work orders stay in the system you already use, such as ServiceChannel, CorrigoPro, ServiceTitan or MaintainX.
The process for our other services.
Tell us about your building.
Call or send a work order. For recurring work we walk the property first, then price it as a fixed monthly agreement or a quoted scope.