How we plan the work.
Planned preventive maintenance means the work is listed, rated and scheduled before anything breaks. We build a register of what your property has, rate every task and set the schedule from those ratings.
| Unit | Observations | Status |
|---|---|---|
| Emergency generator | Starts on test, operable | Surveyed |
| Rooftop unit RTU-1 | Dirty coil, operable | Surveyed |
| Irrigation zones | Two heads out of line | Surveyed |
| Restrooms | Tile floor, six fixtures | Surveyed |
| Server room cooling unit | Keeps the server room online | Surveyed |
Emergency generator3 tasks
Run under load5 stepsCritical
- Check fuel, oil and coolant levels
- Start the generator and bring it up to load
- Record voltage, frequency and run time
- Watch for leaks, smoke or alarms
- Return it to standby and log the run
- Battery and charger check4 stepsImportant
- Fuel sample and tank check4 stepsRecommended
Rooftop unit RTU-14 tasks
- Smoke detector shutdown test4 stepsCritical
- Filter and belt change6 stepsImportant
Condenser coil cleaning5 stepsRecommended
- Lock out the unit and put on the required protective gear
- Protect the surroundings and apply the approved coil cleaner
- Rinse the coil and check for clear airflow across the full face
- Put the guards back and photograph the cleaned coil
- Clean up and dispose of the rinse water to site rules
- Thermal scan of electrical connections4 stepsPremium
Irrigation zones4 tasks
- Check valves and backflow for leaks4 stepsImportant
Run and watch each zone5 stepsRecommended
- Run each zone from the controller
- Walk the zone and watch every head
- Straighten or replace heads that are tilted, clogged or broken
- Check for leaks and wet spots at the valves
- Log repairs with photos
- Clear grass and mulch from heads3 stepsRecommended
- Tune the schedule for the season3 stepsPremium
Restrooms4 tasks
Clean and disinfect fixtures5 stepsCritical
- Put out wet floor signs and prop the door
- Apply disinfectant to toilets, urinals and sinks and let it sit
- Scrub, then wipe each fixture from top to bottom
- Wipe handles, dispensers and partitions
- Check the room and log the visit
- Restock soap, paper and liners3 stepsCritical
- Mop and dry the floor4 stepsRecommended
- Machine scrub tile and grout5 stepsPremium
Server room cooling unit4 tasks
- Filter change3 stepsImportant
- Condensate drain and pan check4 stepsRecommended
- High temperature alarm test3 stepsRecommended
Extra coil and filter service5 stepsPremium
- Confirm the room can run on backup cooling
- Shut down and lock out the unit
- Change the filters and rinse the coil
- Restart and confirm the supply temperature
- Log readings and photos
5 items, 19 tasks in all. Open any one to see its tasks and steps.
| Unit | Nightly | Monthly12 visits a year | Quarterly4 visits a year | Annual1 visit a year |
|---|---|---|---|---|
| Emergency generator | Run under load | Battery and charger check | Fuel sample and tank check | |
| Rooftop unit RTU-1 | Filter and belt change | Smoke detector shutdown testCondenser coil cleaningThermal scan of electrical connections | ||
| Irrigation zones | Check valves and backflow for leaksRun and watch each zoneClear grass and mulch from heads | Tune the schedule for the season | ||
| Restrooms | Clean and disinfect fixturesRestock soap, paper and linersMop and dry the floor | Machine scrub tile and grout | ||
| Server room cooling unit | High temperature alarm test | Filter changeCondensate drain and pan checkExtra coil and filter service |
| Tasks | Two premium tasks held for later | 19 tasks 17 tasks |
| Time | Minutes trimmed on recommended tasks | 46 hours a year 40 hours a year |
| Frequency | One recommended task moved | Quarterly Twice a year |
Critical tasks stay on.
| How far it goes | How we rate each task | Tasks |
|---|---|---|
| Critical | Must be done. We don't compromise on it. | 4 |
| Important | Should be done. Protects the equipment. | 8 |
| Recommended | Worth doing. Prevents problems later. | 15 |
| Premium | For taking the best possible care of it. | 19 |
| Work order | Task | Linked to | Status |
|---|---|---|---|
| WO-1041 | Run under loadEmergency generator | ServiceChannel | OpenDone |
| WO-1042 | Filters and beltsRooftop unit RTU-1 | CorrigoPro | OpenDone |
| WO-1043 | Run and watch each zoneIrrigation zones | ServiceTitan | OpenDone |
| WO-1044 | Clean and restockRestrooms | MaintainX | OpenDone |
| WO-1045 | Extra coil and filter serviceServer room cooling unit | ServiceChannel | OpenDone |
| Task | What the year showed | Next year |
|---|---|---|
| Run under loadEmergency generator | As expected | Monthly |
| Filters and beltsRooftop unit RTU-1 | Filters loading up early | Quarterly Monthly |
| Run and watch each zoneIrrigation zones | As expected | Monthly |
| Clean and restockRestrooms | As expected | Nightly |
| Extra coil and filter serviceServer room cooling unit | As expected | Quarterly |
Six steps, in order.
Each step leaves a record. Scroll to watch an example fill in.
List what the property has
We build an asset register for the property. It lists the equipment, areas and grounds we maintain. The register is kept in M5's own system, and you get a login to it.
Record:Asset registerList and rate the tasks
Each asset gets the tasks that keep it working. Most assets have several, and each task has written steps our team follows. Every task gets one of four ratings: critical, important, recommended or premium. Work required by code or law is critical. Work the manufacturer directs is important.
Record:Rated task listSet how often
How often a task is done follows its rating. The manufacturer's manual is one input. How much your building depends on the asset is the other.
Record:Maintenance scheduleChoose how far the plan goes
The proposal shows what each rating covers. You can stop at critical work or go all the way through premium. Tell us your budget and we show what it covers. We fit the plan to it by adjusting which tasks are in, the time on each task and how often it runs. Critical tasks stay on. Premium is best kept for mission-critical equipment: the one piece that keeps everything in the building running and your business online.
Record:ProposalDo the work in your system
Scheduled work runs as work orders in the system you already use, such as ServiceChannel, CorrigoPro, ServiceTitan or MaintainX. Your team sees it in the same place as every other ticket.
Record:Work ordersReview the plan every year
What we find on each visit goes on the record. Once a year we review the plan with you. We go through the reports, the findings and the past work orders, then adjust the tasks, the schedule and the price for the year ahead. Each year the plan fits the property more closely.
Record:Annual review
A plan can start from your past work orders.When the same repair keeps getting called in, we group those work orders and propose a schedule that does the work before the call.
What each rating covers.
Each rating includes the ones before it. A plan can stop at critical or run all the way through premium.
| No. | Rating | What it means | Where it comes from |
|---|---|---|---|
| 1 | Critical | Must be done. We don't compromise on it. | Work required by code or law |
| 2 | Important | Should be done. Protects the equipment. | Work the manufacturer directs |
| 3 | Recommended | Worth doing. Prevents problems later. | Practical and preferred work |
| 4 | Premium | For taking the best possible care of it. | Discretionary work. Best kept for mission-critical equipment, the one piece that keeps everything in the building running. |
Questions
- We keep calling in the same repairs. Can that become a plan?
- Yes. We look at the work orders you have sent us over time and find the ones that come back on a pattern. We group them and propose a planned maintenance agreement that does that work on a schedule, before it turns into a call. Planned work can cost less than the same work called in one ticket at a time. It works for us too. The work is agreed for a few years, so we can plan our crews around it.
- Do we have to change work order systems?
- No. The asset register is kept in M5's system. The work itself runs in the system you already use, such as ServiceChannel, CorrigoPro, ServiceTitan or MaintainX.
- Who can see the asset register?
- You can. We give you a login, and you see the same register we work from.
The process for each service.
Tell us about your building.
Call or send a work order. For recurring work we walk the property first, then price it as a fixed monthly agreement or a quoted scope.